TARRANT REGIONAL WATER DISTRICT & DALLAS WATER UTILITIES
NAVARRO, TEXAS
ONGOING
WATER
INTEGRATED PIPELINE PROJECT (IPL) – SECTION 17 TRINITY RIVER TUNNEL: The $2.3 billion IPL entails the construction of 149 miles of new pipeline and related infrastructure running from Lake Palestine in East Texas to Benbrook Lake in Tarrant County, with connections to Richland-Chambers and Cedar Creek reservoirs in East Texas. The IPL Section 17 Trinity River Tunnel is a 3,800 linear foot segment, nearly 70% of which tunnels under the Trinity River in Navarro County. D&S provided construction materials engineering testing services for the Section 17 tunneled encasement.
SERVICES / SCOPE OF WORK
Construction Materials Engineering Testing